Sourdough baking as a feedback loop to a better state of mind

On Mar 7, 2020 I started my effort to bake sourdough ordering from King Arthur Baking. I love to cook and have not been a big baker, and decided to give it a try. I was lucky and started this effort before covid got so many others into baking. I had flour, active yeast, and my new sourdough. It has now been over 7 months and I now bake sourdough once every two days. Luckily I got a new gravel ebike that I will write about and ride over a 100 miles a week now and can eat my sourdough without worrying about weight gain.

below is my first batch of baguettes that tasted good, but they looked horrible.

Untitled.jpg

Now my sourdough boules look like this.

Untitled+2.jpg

I have tried different recipes. Different flours. Watched many videos. And got a much better feeling for when the dough is right. Nice thing this got me to experiment with my pizza dough recipes and they got better too.

I knead the dough which some consider a waste of time. I use the kneading time as part of meditation exercise and I figure out many different tough issues. If my mind is not in the right state I cannot see if the dough is right. Seeing things for how they are is one of the hardest things

Untitled 3.jpg

Some ask if I use my pizza over to bake the sourdough. Nope. I use a regular oven and Lodge Dutch oven which makes it so I can easily bake my sourdough when I travel by car and can bring all my supplies. At some point I’ll work on baking sourdough in my pizza oven, but that is much more time consuming. After months of practice I’ve worked on how I bake as if it a classic process engineering problem with my own time and motion studies. Now I can make one batch which is for two loaves. Bake one. Have other for slow fermentation in the fridge. Two days later bake that one. Now I am only making dough twice a week and having fresh sourdough every other day.

After 7 months of baking sourdough I have a regular meditation feedback system that helps me work on tough issues and lets me share bread that is so much better than what I have bought in bakeries or stores.

Great Leadership by Admiral Levering Smith made Polaris success, not PERT

In my research of how PERT became a myth of project management’s power. The key to the success of the Fleet Ballistic Missile program Polaris was great leadership, decentralized organization, and an esprit de corps to save the world from nuclear war. One of the people I ran across was Admiral Levering Smith and reading about the Admiral reminds me of some of the great project managers like Sheila Brady (System 7) and Dennis Adler (Windows 95). I have been lucky to work on both of the operating systems at Apple and Microsoft and saw first hand how these people worked.

Below are highlights from a memorial of Admiral Levering Smith that is here.

Levering knows of his patient, open approach to each new goal—using, and giving credit for, every sound idea and accomplishment. Levering's leadership style was almost the antithesis of that of the textbook, dynamic, emotional leader about which stories are told. He was a leader because he respected the goals of his superiors, respected the responsibilities he had been given, and respected the capabilities of those working for and with him, and he made this apparent to everyone without ever a touch of ego.

Raborn almost immediately drafted Levering from White Sands to lead this work because of his reputation as the navy's preeminent expert on rockets and solid propellants. It was the beginning of an assignment that ultimately produced the most convincing and effective of the nation's strategic deterrent weapon systems.

Levering's planning, which Admiral Raborn accepted, included an innovative and critically important approach to the definition of the requirements toward which everyone on the team worked.

The oceanographers and strategists didn't work in isolation. It was Red's and Levering's contention that the entire team should participate so that each member recognized the critical issues and the relative importance of the goals. A "board of directors" was formed, which was called "the steering task group." Red was the chairman, and Levering was the responsible architect of what the task group was to do. Represented were the leaders of the participating universities, the navy commands who would need to support the program, and the responsible executives of the prime contractors and the critical subcontractors. Part of the strategy was to put on the steering task group not the program directors but their bosses. It was a powerful task force, and it spent three months defining the total program including schedules, costs, performance goals, and the distribution of the task among the members. This was a revolution in management. It wasn't a "method"; it was pure Levering— understand the problem; agree on the approach and risks; and define and agree on the real requirements, the schedule relationships, and the resources required. Once the program was defined and understood, the steering task group met nearly monthly agreeing on changes, modifying plans, and adjusting resources. Everyone was focused on the total task, not an individual element. An example of early goal setting was the range of the Polaris. If the Polaris didn't go 1,200 nautical miles, it couldn't justify its existence; similarly, if its accuracy didn't meet a minimum, it shouldn't be created. However, if the accuracy was adequate and the range approached 1,500 to 2,000 nautical miles, a lot of sea room opened up to improve the invulnerability of the submarine. There were no fixed specifications, just the bottom limits to ensure a total system effectiveness— again, pure Levering. Supplementing this broad policy, Levering Smith and Red Raborn initiated and encouraged a true team effort among the military, civil service personnel, and contractors. Adversarial conditions were quickly sorted out and eliminated. In addition, the facts—failures as well as triumphs—were always available to the world outside of the Department of Defense and Congress as needed. This concept had never penetrated normal Washington procurement mores, but it was the foundation for a monumental success. We must hope that history recognizes Levering's fine hand and mind in creating such an environment. This was real management.

He was what he appeared to be: a highly intelligent, rational, practical engineer with immense respect for those around him, particularly those with good ideas and a reasonable approach to developing them. And above all, he was a gentleman.

To be continued.

The Navy's innovative moves to be significant part of the US's Nuclear deterrent strategy, politics and technology

Harvey Sapolsky is Professor of Public Policy and Organization and recently retired from teaching political science and directing the MIT Security Studies Program. In one of the e-mail conversations I had with Harvey I asked how did he get the job from the Navy to analyze the Fleet Ballistic Missile program (Polaris) to understand why it worked so well. Harvey interviewed a huge set of people and understanding how he got the job helps get a perspective on how he conducted the research.

Over four hundred interviews were con- ducted ranging in length from a minimum of one hour to repeat sessions that total over forty hours with one individual. Among those interviewed were persons in other naval organizations, contractor organizations, the Army, the Air Force, the Department of Defense, the Atomic Energy Commission, the Congress, the General Accounting Office, the National Aeronautics and Space Administration, the Ceneral Intelligence Agency, and the British Admiralty.

Harvey’s PhD thesis advisor was James Q. Wilson whose achievements are in this Britannica article which include a Presidential Medal of Freedom in 2003 and James’s first PhD student was Harvey Sapolsky and James helped launch his career by suggesting Harvey as a person who could do the research on FBM for the navy.

One of the papers Harvey published on the missile program is here. What was fascinating is to read that the Navy tricked the Air Force into approving resources for the Polaris missile in exchange for the Navy withdrawing from the Army’s Intermediate Range Ballistic Missile program. The Air Force was much more concerned about the Army having nuclear launch capability than the Navy. The Navy realized that the Army’s liquid fuel missile was not a good fit for launching missile's from a submarine and solid rocket fuel was much better. It is like driving in your car with a 5 gal can of gasoline versus a 50 lb bag of charcoal in the back. And the Army’s missile design was much too big to fit in a submarine.

So the Navy made a deal to withdraw from the Army’s nuclear missile efforts if the Air Force would support their own solid rocket fuel efforts. the Air Force agreed and that was the start of the Polaris missile program.

The obstacles for the Navy to develop submarine launched ballistic missile were huge.

By any measure SLBMs were a significant innovation, affecting in important ways several dimensions of U.S. strategic policy. They helped kill as unneeded a vast bomber force (our own), helped save the Navy from being marginalized in the assignment of the nation’s most vital security mission, and helped win the Cold War by making it impossible for the United States to lose. They also were largely unwanted both within and without the Navy. Civilians did not want the Navy to develop its own ballistic missile. The Air Force criticized the effort. The Army had to be pushed out of the way. And much of the Navy dreaded SLBMs.

To overcome the organizations who wanted the Polaris program to fail it was decided protecting the development team from outside attacks was critical. There needed to be a way to defend the project and its resources. That is where the basis from PERT and professional project management came from. To create perception of a perfectly run project. Pretty charts and graphics. Alternatives are evaluated and optimized by computer. It looks like everything is inventoried and accounted for. The schedule was totally predictable.

Special Projects Office's reputation seems not only to have been beneficial, but also to have been in large part contrived.

FBM proponents saw a competitive advantage in having the Special Projects Office perceived as possessing an extraordinarily ef- fective management system.

men who recognized that management systems could have political as well as operational benefits.

One of the best example I found on how smart the project team was and how PERT was not the true representation of the project is the below Table which shows the multiple vendors used for each component. How do you put all those vendors with each of their different project events in one PERT diagram? Did you just list the generic areas and assume a vendor would do that work? if you did your schedule was not that accurate. Did you you list each vendor as alternative suppliers for a given amount of work?

This supplier strategy was part of Admiral Levering Smith’s design of the highly modularized component design with at least three suppliers available for any component.

Untitled 7.png

Amazing Project Change, When asked to deliver Polaris submarine launched nuclear missile launch faster, response is 3 years

The Polaris Missile program is recognized as one of the most successful complex projects. How good was the program. The London Daily telegraph wrote the following regarding the UK’s efforts to deploy Polaris in their fleet.

The London Daily Telegraph: "It was no small measure due to him [Levering Smith] that the British Polaris programme was completed on time and on budget—an unprecedented feat in British naval history."

Even more amazing though is after Russia launched Sputnik I into orbit in 1957 there was a call to Admiral Raborn to see if he could improve the schedule of Polaris. After a week he said if they would accept a 1200 mile range instead of 1500 he could get the program operational by 1960, three years ahead of schedule. They accepted of course.

Who does that on a project? How did they do it? This is one of the facts that got me more interested to understand what went on.

The simple answer is they created a fork in the project and they created another project that was scheduled for 1960 and in parallel there was another project following the original plan for 1963 with extended range. This project used a lot of existing technology and components. And they used Agile methodology.

Agile methodology is a type of project management process, mainly used for software development, where demands and solutions evolve through the collaborative effort of self-organizing and cross-functional teams and their customers.

Where was this shown? There is nothing about being Agile written. Here is what they did in 1958.

Sixty-odd test firings of live prototype Polaris missiles were stage between January 1958 and the July 20th shot.

Of these, two were termed outright failures, 20 were rated as partial successes, the remainder complete successes. Even the failures and partial successes were successes in a way, for they revealed flaws which could be corrected or eliminated in future shots.

That is two rocket launches a week. What project schedule and project managers could plan that? It would take weeks just to collect the data to update the schedule and how many meetings would be held for each of those sixty-odd firings.

So even though PERT and project managers were used they do not support how this could be done. No amount of project analysis would shave 3 years off a schedule. I’ll explain more on how this happened in another post. If you are interested in reading what the Navy published in 1960 here is the article. https://quietwarriors.files.wordpress.com/2014/03/all-hands-sep-1960-polaris_a-success-story.pdf

Project Managers #1 job is their own survival, not the success of the project!

I’ve spent many years as a project manager/program manager and know many other great leaders of the Mac II, System 7, Windows 95, and they all the talent to rally the teams to work together like Gung Ho is used. Being a project manager has grown into certified profession with its vocabulary embraced by consultants to manage complex projects.

Professional project managers almost all know that the big start was in the creation of PERT for the Polaris missile program.

“PERT” was developed primarily to simplify the planning and scheduling of large and complex projects. It was developed for the U.S. Navy Special Projects Office in 1957 to support the U.S. Navy’s Polaris nuclear submarine project.[2] It found applications all over industry. An early example was it was used for the 1968 Winter Olympics in Grenoble which applied PERT from 1965 until the opening of the 1968 Games.[3] This project model was the first of its kind, a revival for scientific management, founded by Frederick Taylor (Taylorism) and later refined by Henry Ford (Fordism). DuPont’s critical path method was invented at roughly the same time as PERT.
— https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique

Chatting with a close friend on how project managers should support a project and whether the person should come from corporate on the field. Thinking about this issue for a week I came back and said well the main problem you have with project managers is the way they are wired to work these days is their #1 goal is their own survival and create processes that protect them and when things go wrong it is not their fault, but others. We laughed.

To back up my point I decided to go to the source and bought a used copy of “The Polaris System Development” book by Harvey Sapolsky. Here is one paragraph where Harvey says there was no ROI for PERT as an analysis would shatter the myth that PERT was perfect in its planning.

The Special Projects Office never has attempted to measure the effectiveness of PERT; the reputational cost of a negative finding would prove too costly for the organization to bear. Moreover, such a study would be somewhat pointless whatever its results since PERT-type systems are now a Department of Defense requirement on FBM and other weapon development contracts. Yet subjective evaluations of PERT do exist in the Special Projects Office, the birthplace of the PERT system. As one senior officer stated, “We would seek an immediate exemp- tion for the OSD requirement but it isn’t worth the fight. They apparently believe in it and they pay for it.”

The best part about doing this research is I have had numerous e-mail conversations with Harvey Sapolsky and understand his research so much better and what was the true skills developed during the Polaris Project to ship a game changing technology that has changed nuclear weaponry.